Equipment list & Location

We have decided to shoot our television advert in the Sidney Stringer Academy theatre for three consecutive weeks (11/03/13, 18/03/13, 25/03/13). We have gained permission to use the location for the three weeks from the timings of 1.00pm - 4.00pm.

The equipment and props that we need by the 11th March 2013 are;

  • HD Canon camera and charger
  • SD memory card and reader
  • Tripod
  • Apple mac
  • key, background and filler lights
  • black, white and patterned backdrops
  • alcohol bottles
  • sheesha pot
  • chair
  • clothing items (clothes, shoes, jewellery, accessories)
  • Make-up/hair products
  • projector
  • Music device (to play sound track to help us remember/include the beat of the songs)
Shooting schedule

Date
Task
What needs to be done
04/02/2013
Pre - production
Got the brief and mind mapped ideas down for our advertisement product.

Carried out tasks like;
-Mind map
-mood board
-word board

11/02/2013
Pre - production
Finalised out theme and idea for our advert. Did some research on similar existing fashion adverts.

Carried out tasks like;
-Storyboard
-mind map
-Analysis of existing adverts

18/02/2013
Pre - production
Added structure to our advert idea. Brainstormed ideas for start middle and end. Product forming.

Carried out tasks like;
-Story board
-mise-en-scene
-considering target audience
-characteristics of advertising

25/02/2013
Pre - production
Carried out various pre-production tasks. Carried out a focus group for further research ideas on our product.

Carried out tasks like;
-Focus group filming
-treatment/proposal
-risk assessment
-music/sounds

04/03/2013
Pre - production
Carried out various pre-production tasks. Got permission for location and models.

Carried out tasks like;
-looking and asking for permission for location space and models
-collecting and gathering props
-working out the budget

11/03/2013
Production
Filming first part of advert (Males scene)

Carried out tasks like;
-Setting up
-getting the model ready and revised of the scene
-directing and recording scenes
-being aware of health and safety risks

18/03/2013
Production
Filming second part of advert (Females scene)

Carried out tasks like;
-Setting up
-getting the model ready and revised of the scene
-directing and recording scenes
-being aware of health and safety risks

25/03/2013
Post - production
Editing the collected scenes so far (female part) on Adobe Premier Pro CS4
01/04/2013
Holiday
 -
08/04/2013
Holiday
 -
15/04/2013
Post - production
Editing the collected scenes so far (female part) on Adobe Premier Pro CS4 and finishing off any incomplete blog work
22/04/2013
Production
Filming final part of advert (Male and female joining)

Carried out tasks like;
-Setting up
-getting the model ready and revised of the scene
-directing and recording scenes
-being aware of health and safety risks

29/04/2013
Post - production
Editing the collected scenes so far (female part) on Adobe Premier Pro CS4 and finishing off any incomplete blog work
06/05/2013
Post - production
Deadline for media production. Evaluating and receiving feedback.


The shooting schedule does not include any out of hours filming or work. Tasks will also be carried out throughout the week to ensure we keep on top of our schedule.